BetaActiveSolarIPLBNL
280 MW generation in Bingham, ID · In queue since September 2023 · Proposed COD December 2027
280 MW
Capacity
1
Components
Solar
2y 6m
In Queue
IA Executed
IA Status
Signed Dec 1999
Interconnection Timeline
IA → COD
28 years
Total Duration
2y 6m
Construction75%
Queue EntrySep 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementDec 31, 1999
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
ID
County
Bingham
Region
West
Developer
—
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
BRDY-ANTS 230kV
Data Source
LBNL
No news available for this project.