— Project Summary

Queue ID
IP-708
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Ada, ID
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryIPLBNL

150 MW hybrid in Ada, ID · In queue since March 2023 · Proposed COD December 2028

150 MW

Capacity

1

Components

Solar

3 years

In Queue

IA Executed

IA Status

Signed Dec 1999

Interconnection Timeline

IA → COD

29 years

Total Duration

3 years

Construction75%
Queue EntryMar 27, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementDec 31, 1999

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

ID

County

Ada

Region

West

Developer

Utility

Idaho Power Company

Entity

IP

Point of Interconnection

Hubbard-Danskin 230kV Line

Data Source

LBNL

No news available for this project.