BetaActiveSolarIPLBNL
330 MW generation in Twin Falls, ID · In queue since February 2023 · Proposed COD December 2025
330 MW
Capacity
1
Components
Solar
3y 1m
In Queue
IA Executed
IA Status
Signed Dec 1999
Interconnection Timeline
IA → COD
26 years
Total Duration
3y 1m
Schedule
3 months past proposed COD
Construction75%
Queue EntryFeb 17, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementDec 31, 1999
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
ID
County
Twin Falls
Region
West
Developer
—
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Midpoint_x0013_Hemingway 500kV Line
Data Source
LBNL
No news available for this project.