330 MW storage in Owyhee, ID · In queue since December 2022 · Proposed COD June 2026
330 MW
Capacity
1
Components
Battery
3y 3m
In Queue
IA Executed
IA Status
Signed Jan 2024
Interconnection Timeline
Queue → IA
1y 1m
IA → COD
2y 5m
Total Duration
1y 1m
Construction75%
Queue EntryDec 28, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementJan 29, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
ID
County
Owyhee
Region
West
Developer
KCE ID 1, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Hemingway 230kV Substation
Data Source
LBNL