— Project Summary

Queue ID
IP-667
Capacity
400 MW
Technology
Solar+Battery
Status
suspended
Location
Elmore, ID
Region
West
Developer
Martha Fields Energy Center, LLC
IA Status
IA Executed

BetaSuspendedSolarBatteryIPLBNL

400 MW hybrid in Elmore, ID · In queue since August 2022 · Proposed COD December 2026

400 MW

Capacity

1

Components

Solar

3y 7m

In Queue

IA Executed

IA Status

Signed Mar 2024

Interconnection Timeline

Queue → IA

1y 7m

IA → COD

2y 9m

Total Duration

1y 7m

Suspended75%
Queue EntryAug 17, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementMar 7, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

ID

County

Elmore

Region

West

Developer

Martha Fields Energy Center, LLC

Utility

Idaho Power Company

Entity

IP

Point of Interconnection

BOBN_x0013_MPSN #2 230kV Line

Data Source

LBNL

No news available for this project.