200 MW hybrid in Canyon, ID · In queue since August 2022 · Proposed COD December 2026
200 MW
Capacity
1
Components
Solar
3y 7m
In Queue
IA Executed
IA Status
Signed Nov 2023
Interconnection Timeline
Queue → IA
1y 3m
IA → COD
3y 1m
Total Duration
1y 3m
Suspended75%
Queue EntryAug 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementNov 2, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
ID
County
Canyon
Region
West
Developer
Powers Butte Energy Center, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Bowmont 138kV Substation
Data Source
LBNL