1,000 MW hybrid in Power, ID · In queue since June 2022 · Proposed COD December 2025
1,000 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Status
Signed Feb 2024
Interconnection Timeline
Queue → IA
1y 8m
IA → COD
1y 10m
Total Duration
1y 8m
Suspended75%
Queue EntryJun 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementFeb 1, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
ID
County
Power
Region
West
Developer
Sawtooth DevCo, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Borah 345kV Substation
Data Source
LBNL