BetaSuspendedSolarGasBatteryIPLBNL
1,650 MW hybrid in Owyhee, ID · In queue since June 2022 · Proposed COD December 2025
1,650 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Status
Signed Sep 2023
Interconnection Timeline
Queue → IA
1y 3m
IA → COD
2y 3m
Total Duration
1y 3m
Suspended75%
Queue EntryJun 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementSep 12, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
ID
County
Owyhee
Region
West
Developer
Sawtooth DevCo, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Hemingway 500kV Substation
Data Source
LBNL
No news available for this project.