325 MW hybrid in Bear Lake, ID · In queue since May 2022 · Proposed COD December 2025
325 MW
Capacity
1
Components
Solar
3y 10m
In Queue
IA Executed
IA Status
Signed Dec 2023
Interconnection Timeline
Queue → IA
1y 7m
IA → COD
2 years
Total Duration
1y 7m
Schedule
3 months past proposed COD
Construction75%
Queue EntryMay 10, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementDec 14, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
ID
County
Bear Lake
Region
West
Developer
Aurora Solar LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Bridger_x0013_Populus 345kV Line
Data Source
LBNL