BetaActiveSolarBatteryIPLBNL
130 MW hybrid in Bingham, ID · In queue since May 2022 · Proposed COD December 2025
130 MW
Capacity
1
Components
Solar
3y 10m
In Queue
IA Executed
IA Status
Signed Nov 2023
Interconnection Timeline
Queue → IA
1y 6m
IA → COD
2y 1m
Total Duration
1y 6m
Schedule
3 months past proposed COD
Construction75%
Queue EntryMay 3, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementNov 2, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
ID
County
Bingham
Region
West
Developer
Pingree Solar LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Pingree 138kV Substation
Data Source
LBNL
No news available for this project.