BetaSuspendedBatteryIPLBNL
200 MW storage in Power, ID · In queue since February 2022 · Proposed COD December 2024
200 MW
Capacity
1
Components
Battery
4y 1m
In Queue
IA Executed
IA Status
Signed Apr 2023
Interconnection Timeline
Queue → IA
1y 2m
IA → COD
1y 8m
Total Duration
1y 2m
Suspended75%
Queue EntryFeb 25, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementApr 27, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 6–18 months
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
ID
County
Power
Region
West
Developer
Fresh Air Energy II, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
BRDY 230kV Substation
Data Source
LBNL
No news available for this project.