BetaActiveBatteryIPLBNL
150 MW storage in Ada, ID · In queue since February 2022 · Proposed COD June 2026
150 MW
Capacity
1
Components
Battery
4y 1m
In Queue
IA Executed
IA Status
Signed May 2023
Interconnection Timeline
Queue → IA
1y 3m
IA → COD
3y 1m
Total Duration
1y 3m
Construction75%
Queue EntryFeb 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementMay 12, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
ID
County
Ada
Region
West
Developer
Idaho Power Company_x0014_Power Supply
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Boise Bench Substation 138kV
Data Source
LBNL
No news available for this project.