BetaActiveSolarIPLBNL
149 MW generation in Elmore, ID · In queue since February 2022 · Proposed COD December 2025
149 MW
Capacity
1
Components
Solar
4y 1m
In Queue
IA Executed
IA Status
Signed Mar 2024
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
1y 9m
Total Duration
2y 1m
Schedule
3 months past proposed COD
Construction75%
Queue EntryFeb 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementMar 13, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
ID
County
Elmore
Region
West
Developer
Soles Rest Solar LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Danskin_x0013_Hubbard 230kV Line
Data Source
LBNL
No news available for this project.