1,000 MW hybrid in Gooding, ID · In queue since February 2022 · Proposed COD December 2026
1,000 MW
Capacity
1
Components
Solar
4y 1m
In Queue
IA Executed
IA Status
Signed Jun 2023
Interconnection Timeline
Queue → IA
1y 4m
IA → COD
3y 6m
Total Duration
1y 4m
Suspended75%
Queue EntryFeb 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementJun 13, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
ID
County
Gooding
Region
West
Developer
Taurus Wind LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Midpoint 500kV Substation
Data Source
LBNL