BetaActiveBatteryIPLBNL
13 MW storage in Owyhee, ID · In queue since January 2022 · Proposed COD June 2024
13 MW
Capacity
1
Components
Battery
4y 2m
In Queue
IA Executed
IA Status
Signed Jan 2023
Interconnection Timeline
Queue → IA
1 year
IA → COD
1y 5m
Total Duration
1 year
Schedule
22 months past proposed COD
Construction75%
Queue EntryJan 25, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementJan 20, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
ID
County
Owyhee
Region
West
Developer
Idaho Power Company_x0014_Power Supply
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Hemingway 34.5kV
Data Source
LBNL
No news available for this project.