300 MW hybrid in Owyhee, ID · In queue since January 2022 · Proposed COD December 2025
300 MW
Capacity
1
Components
Solar
4y 2m
In Queue
IA Executed
IA Status
Signed Oct 2023
Interconnection Timeline
Queue → IA
1y 9m
IA → COD
2y 2m
Total Duration
1y 9m
Schedule
3 months past proposed COD
Construction75%
Queue EntryJan 14, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementOct 18, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
ID
County
Owyhee
Region
West
Developer
NextEra Energy Resources Interconnection Holdings, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Hemingway 230kV Substation
Data Source
LBNL
No news available for this project.