BetaSuspendedSolarBatteryIPLBNL
200 MW hybrid in Jerome, ID · In queue since October 2021 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Status
Signed Sep 2023
Interconnection Timeline
Queue → IA
1y 11m
IA → COD
2y 3m
Total Duration
1y 11m
Suspended75%
Queue EntryOct 26, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementSep 18, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
ID
County
Jerome
Region
West
Developer
Invenergy Solar Project Development LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Midpoint 230kV Switchyard
Data Source
LBNL
No news available for this project.