BetaSuspendedSolarIPLBNL
200 MW generation in Bingham, ID · In queue since October 2021 · Proposed COD June 2025
200 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Status
Signed Nov 2022
Interconnection Timeline
Queue → IA
1y 1m
IA → COD
2y 7m
Total Duration
1y 1m
Suspended75%
Queue EntryOct 20, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementNov 10, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
ID
County
Bingham
Region
West
Developer
Mosby Butte Solar, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Brady_x0013_Antelope 230kV Line
Data Source
LBNL
No news available for this project.