— Project Summary

Queue ID
IP-622
Capacity
600 MW
Technology
Battery
Status
active
Location
Malheur, OR
Region
West
Developer
Owyhee Energy Storage, LLC
IA Status
IA Executed

BetaActiveOther StorageIPLBNL

600 MW storage in Malheur, OR · In queue since October 2021 · Proposed COD August 2028

600 MW

Capacity

1

Components

Other Storage

4y 5m

In Queue

IA Executed

IA Status

Signed May 2023

Interconnection Timeline

Queue → IA

1y 7m

IA → COD

5y 3m

Total Duration

1y 7m

Construction75%
Queue EntryOct 18, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementMay 1, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-08-31

Project Details

State

OR

County

Malheur

Region

West

Developer

Owyhee Energy Storage, LLC

Utility

Idaho Power Company

Entity

IP

Point of Interconnection

HMWY_x0013_SMLK 500kV Line

Data Source

LBNL