— Project Summary

Queue ID
IP-614
Capacity
132 MW
Technology
Wind+Battery
Status
suspended
Location
Twin Falls, ID
Region
West
Developer
Magic Valley Energy, LLC
IA Status
IA Executed

BetaSuspendedWindBatteryIPLBNL

132 MW hybrid in Twin Falls, ID · In queue since August 2021 · Proposed COD December 2025

132 MW

Capacity

1

Components

Wind

4y 7m

In Queue

IA Executed

IA Status

Signed Sep 2023

Interconnection Timeline

Queue → IA

2y 1m

IA → COD

2y 3m

Total Duration

2y 1m

Suspended75%
Queue EntryAug 6, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementSep 22, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 24–36 months

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

ID

County

Twin Falls

Region

West

Developer

Magic Valley Energy, LLC

Utility

Idaho Power Company

Entity

IP

Point of Interconnection

Rogerson 345kV Substation

Data Source

LBNL

No news available for this project.