132 MW hybrid in Twin Falls, ID · In queue since August 2021 · Proposed COD December 2025
132 MW
Capacity
1
Components
Wind
4y 7m
In Queue
IA Executed
IA Status
Signed Sep 2023
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
2y 3m
Total Duration
2y 1m
Suspended75%
Queue EntryAug 6, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementSep 22, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 24–36 months
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
ID
County
Twin Falls
Region
West
Developer
Magic Valley Energy, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Rogerson 345kV Substation
Data Source
LBNL