— Project Summary

Queue ID
IP-609
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Sweetwater, WY
Region
West
Developer
NextEra Energy Resources Interconnection Holdings, LLC
IA Status
IA Executed

BetaActiveSolarWindBatteryIPLBNL

200 MW hybrid in Sweetwater, WY · In queue since June 2021 · Proposed COD December 2025

200 MW

Capacity

1

Components

Solar

4y 9m

In Queue

IA Executed

IA Status

Signed May 2023

Interconnection Timeline

Queue → IA

1y 11m

IA → COD

2y 7m

Total Duration

1y 11m

Schedule

4 months past proposed COD

Construction75%
Queue EntryJun 28, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementMay 9, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

WY

County

Sweetwater

Region

West

Developer

NextEra Energy Resources Interconnection Holdings, LLC

Utility

Idaho Power Company

Entity

IP

Point of Interconnection

JBRG 345kV Substation

Data Source

LBNL

No news available for this project.