BetaActiveSolarWindBatteryIPLBNL
200 MW hybrid in Sweetwater, WY · In queue since June 2021 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
4y 9m
In Queue
IA Executed
IA Status
Signed May 2023
Interconnection Timeline
Queue → IA
1y 11m
IA → COD
2y 7m
Total Duration
1y 11m
Schedule
4 months past proposed COD
Construction75%
Queue EntryJun 28, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementMay 9, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
WY
County
Sweetwater
Region
West
Developer
NextEra Energy Resources Interconnection Holdings, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
JBRG 345kV Substation
Data Source
LBNL
No news available for this project.