BetaSuspendedSolarBatteryIPLBNL
240 MW hybrid in Elmore, ID · In queue since May 2021 · Proposed COD December 2024
240 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Executed
IA Status
Signed Apr 2023
Interconnection Timeline
Queue → IA
1y 11m
IA → COD
1y 8m
Total Duration
1y 11m
Suspended75%
Queue EntryMay 27, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementApr 20, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
ID
County
Elmore
Region
West
Developer
South Bennett Solar LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
RTSN 230kV Substation
Data Source
LBNL
No news available for this project.