BetaActiveSolarBatteryIPLBNL
100 MW hybrid in Elmore, ID · In queue since May 2021 · Proposed COD December 2024
100 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Executed
IA Status
Signed Jan 2023
Interconnection Timeline
Queue → IA
1y 8m
IA → COD
1y 11m
Total Duration
1y 8m
Schedule
16 months past proposed COD
Construction75%
Queue EntryMay 27, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementJan 24, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
ID
County
Elmore
Region
West
Developer
Crimson Orchard Solar LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Danskin 230kV Substation
Data Source
LBNL