BetaActiveSolarIPLBNL
125 MW generation in Ada, ID · In queue since September 2020 · Proposed COD October 2024
125 MW
Capacity
1
Components
Solar
5y 6m
In Queue
IA Executed
IA Status
Signed Sep 2022
Interconnection Timeline
Queue → IA
2 years
IA → COD
2y 1m
Total Duration
2 years
Schedule
18 months past proposed COD
Construction75%
Queue EntrySep 10, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementSep 14, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2024-10-01
Project Details
State
ID
County
Ada
Region
West
Developer
PVS 2, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Hubbard_x0013_Danskin 230kV
Data Source
LBNL
No news available for this project.