— Project Summary

Queue ID
IP-588
Capacity
125 MW
Technology
Solar
Status
active
Location
Ada, ID
Region
West
Developer
PVS 2, LLC
IA Status
IA Executed

BetaActiveSolarIPLBNL

125 MW generation in Ada, ID · In queue since September 2020 · Proposed COD October 2024

125 MW

Capacity

1

Components

Solar

5y 6m

In Queue

IA Executed

IA Status

Signed Sep 2022

Interconnection Timeline

Queue → IA

2 years

IA → COD

2y 1m

Total Duration

2 years

Schedule

18 months past proposed COD

Construction75%
Queue EntrySep 10, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementSep 14, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2024-10-01

Project Details

State

ID

County

Ada

Region

West

Developer

PVS 2, LLC

Utility

Idaho Power Company

Entity

IP

Point of Interconnection

Hubbard_x0013_Danskin 230kV

Data Source

LBNL

No news available for this project.