BetaSuspendedWindBatteryIPLBNL
1,050 MW hybrid in Jerome, ID · In queue since August 2020 · Proposed COD December 2023
1,050 MW
Capacity
1
Components
Wind
5y 7m
In Queue
IA Executed
IA Status
Signed Mar 2022
Interconnection Timeline
Queue → IA
1y 7m
IA → COD
1y 9m
Total Duration
1y 7m
Suspended75%
Queue EntryAug 5, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementMar 23, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 24–36 months
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
ID
County
Jerome
Region
West
Developer
Magic Valley Energy, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
MPSN 345kV
Data Source
LBNL
No news available for this project.