BetaActiveSolarBatteryIPLBNL
300 MW hybrid in Power, ID · In queue since November 2019 · Proposed COD November 2022
300 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Status
Signed Oct 2021
Interconnection Timeline
Queue → IA
1y 11m
IA → COD
1y 1m
Total Duration
1y 11m
Schedule
40 months past proposed COD
Construction75%
Queue EntryNov 2, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementOct 5, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2022-11-30
Project Details
State
ID
County
Power
Region
West
Developer
NextEra Energy Resources Interconnection Holdings, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
BORA 345kV Substation
Data Source
LBNL