BetaSuspendedWindBatteryIPLBNL
1,050 MW hybrid in Jerome, ID · In queue since October 2019 · Proposed COD December 2023
1,050 MW
Capacity
1
Components
Wind
6y 5m
In Queue
IA Executed
IA Status
Signed Mar 2022
Interconnection Timeline
Queue → IA
2y 5m
IA → COD
1y 9m
Total Duration
2y 5m
Suspended75%
Queue EntryOct 17, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementMar 23, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 24–36 months
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
ID
County
Jerome
Region
West
Developer
Magic Valley Energy, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
MPSN 500kV
Data Source
LBNL