200 MW generation in Ada, ID · In queue since September 2019 · Proposed COD November 2023
200 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
Signed Sep 2022
Interconnection Timeline
Queue → IA
3 years
IA → COD
1y 2m
Total Duration
3 years
Schedule
29 months past proposed COD
Construction75%
Queue EntrySep 13, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementSep 14, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2023-11-01
Project Details
State
ID
County
Ada
Region
West
Developer
Pleasant Valley Solar, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Danskin_x0013_Hubbard 230kV Line
Data Source
LBNL
No news available for this project.