BetaSuspendedSolarIPLBNL
120 MW generation in Jerome, ID · In queue since May 2019 · Proposed COD December 2020
120 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Status
Signed Jul 2021
Interconnection Timeline
Queue → IA
2y 2m
Total Duration
2y 2m
Suspended75%
Queue EntryMay 14, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementJul 30, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2020-12-01
Project Details
State
ID
County
Jerome
Region
West
Developer
Cat Creek Energy, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Hunt_x0013_Milner 138kV Line
Data Source
LBNL
No news available for this project.