BetaActiveSolarBatteryIPLBNL
40 MW hybrid in Elmore, ID · In queue since April 2019 · Proposed COD December 2023
40 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Status
Signed Aug 2021
Interconnection Timeline
Queue → IA
2y 4m
IA → COD
2y 4m
Total Duration
2y 4m
Schedule
28 months past proposed COD
Construction75%
Queue EntryApr 3, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementAug 27, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
ID
County
Elmore
Region
West
Developer
Black Mesa Interconnection, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Black Mesa 138kV Substation
Data Source
LBNL
No news available for this project.