BetaSuspendedSolarBatteryIPLBNL
30 MW hybrid in Grant, OR · In queue since April 2019 · Proposed COD November 2021
30 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Status
Signed Aug 2021
Interconnection Timeline
Queue → IA
2y 4m
IA → COD
3 months
Total Duration
2y 4m
Suspended75%
Queue EntryApr 30, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementAug 4, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Proposed COD: 2021-11-30
Project Details
State
OR
County
Grant
Region
West
Developer
Prairie City PV1, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
QUTZ_x0013_WJDY 138kV Substation
Data Source
LBNL
No news available for this project.