— Project Summary

Queue ID
IP-551
Capacity
240 MW
Technology
Solar+Battery
Status
suspended
Location
Elmore, ID
Region
West
Developer
Bennett Solar B LLC
IA Status
IA Executed

BetaSuspendedSolarBatteryIPLBNL

240 MW hybrid in Elmore, ID · In queue since April 2019 · Proposed COD December 2022

240 MW

Capacity

1

Components

Solar

6y 11m

In Queue

IA Executed

IA Status

Signed Nov 2021

Interconnection Timeline

Queue → IA

2y 7m

IA → COD

1y 1m

Total Duration

2y 7m

Suspended75%
Queue EntryApr 8, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementNov 19, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 18–30 months

Commercial Operation

Proposed COD: 2022-12-01

Project Details

State

ID

County

Elmore

Region

West

Developer

Bennett Solar B LLC

Utility

Idaho Power Company

Entity

IP

Point of Interconnection

RTSN 230kV

Data Source

LBNL

No news available for this project.