BetaActiveSolarIPLBNL
3 MW generation in Baker, OR · In queue since December 2018 · Proposed COD December 2019
3 MW
Capacity
1
Components
Solar
7y 3m
In Queue
IA Executed
IA Status
Signed Aug 2021
Interconnection Timeline
Queue → IA
2y 8m
Total Duration
2y 8m
Schedule
77 months past proposed COD
Construction75%
Queue EntryDec 18, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementAug 26, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2019-12-01
Project Details
State
OR
County
Baker
Region
West
Developer
Durkee Solar, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
DRKE 12.47kV Feeder
Data Source
LBNL