BetaSuspendedSolarWindOther StorageIPLBNL
870 MW hybrid in Elmore, ID · In queue since April 2018 · Proposed COD December 2020
870 MW
Capacity
1
Components
Solar
7y 11m
In Queue
IA Executed
IA Status
Signed Oct 2021
Interconnection Timeline
Queue → IA
3y 6m
Total Duration
3y 6m
Suspended75%
Queue EntryApr 23, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementOct 12, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Proposed COD: 2020-12-12
Project Details
State
ID
County
Elmore
Region
West
Developer
Cat Creek Energy, LLC
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
RattleCat 230kV Substation
Data Source
LBNL