BetaActiveSolarBatteryIIDLBNL
100 MW hybrid in Imperial, CA · In queue since April 2023 · Proposed COD December 2026
100 MW
Capacity
1
Components
Solar
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 8m
In Study38%
Queue EntryApr 27, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
CA
County
Imperial
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
92kV C
Data Source
LBNL