BetaActiveBatteryIIDLBNL
387 MW storage in Imperial, CA · In queue since April 2023 · Proposed COD April 2025
387 MW
Capacity
1
Components
Battery
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2 years
Schedule
12 months past proposed COD
In Study38%
Queue EntryApr 4, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-04-01
Project Details
State
CA
County
Imperial
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
230kV ECSS
Data Source
LBNL
No news available for this project.