— Project Summary

Queue ID
IID-GI-2023-166
Capacity
100 MW
Technology
Battery
Status
active
Location
Imperial, CA
Region
West
Developer
IA Status
System Impact Study

BetaActiveBatteryIIDLBNL

100 MW storage in Imperial, CA · In queue since January 2023 · Proposed COD June 2024

100 MW

Capacity

1

Components

Battery

3y 2m

In Queue

System Impact Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 5m

Schedule

22 months past proposed COD

Impact Study25%
Queue EntryJan 10, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-06-01

Project Details

State

CA

County

Imperial

Region

West

Developer

Utility

Imperial Irrigation District

Entity

IID

Point of Interconnection

92kV L line

Data Source

LBNL

No news available for this project.