— Project Summary

Queue ID
IID-GI-2023-165
Capacity
50 MW
Technology
Solar+Battery
Status
active
Location
Imperial, CA
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryIIDLBNL

50 MW hybrid in Imperial, CA · In queue since January 2023 · Proposed COD October 2025

50 MW

Capacity

1

Components

Solar

3y 2m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 9m

Schedule

6 months past proposed COD

Impact Study25%
Queue EntryJan 9, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-01

Project Details

State

CA

County

Imperial

Region

West

Developer

Utility

Imperial Irrigation District

Entity

IID

Point of Interconnection

161kV A line

Data Source

LBNL

No news available for this project.