BetaActiveSolarBatteryIIDLBNL
800 MW hybrid in Imperial, CA · In queue since November 2022 · Proposed COD March 2026
800 MW
Capacity
1
Components
Solar
3y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 4m
Schedule
1 months past proposed COD
In Study38%
Queue EntryNov 30, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-01
Project Details
State
CA
County
Imperial
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
Proposed New Facility
Data Source
LBNL
No news available for this project.