BetaActiveSolarBatteryIIDLBNL
125 MW hybrid in Riverside, CA · In queue since September 2022 · Proposed COD December 2025
125 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 3m
Schedule
4 months past proposed COD
In Study38%
Queue EntrySep 12, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
CA
County
Riverside
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
230kV KN/KS line
Data Source
LBNL