BetaActiveBatteryIIDLBNL
60 MW storage in Imperial, CA · In queue since September 2022 · Proposed COD December 2024
60 MW
Capacity
1
Components
Battery
3y 6m
In Queue
System Impact Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 3m
Schedule
16 months past proposed COD
Impact Study25%
Queue EntrySep 6, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
CA
County
Imperial
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
92kV E line
Data Source
LBNL
No news available for this project.