— Project Summary

Queue ID
IID-GI-2022-157
Capacity
65 MW
Technology
Solar+Battery
Status
active
Location
Imperial, CA
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryIIDLBNL

65 MW hybrid in Imperial, CA · In queue since September 2022 · Proposed COD December 2024

65 MW

Capacity

1

Components

Solar

3y 6m

In Queue

System Impact Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 3m

Schedule

16 months past proposed COD

Impact Study25%
Queue EntrySep 6, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-01

Project Details

State

CA

County

Imperial

Region

West

Developer

Utility

Imperial Irrigation District

Entity

IID

Point of Interconnection

92kV R line

Data Source

LBNL

No news available for this project.