BetaActiveSolarBatteryIIDLBNL
100 MW hybrid in Imperial, CA · In queue since February 2022 · Proposed COD September 2024
100 MW
Capacity
1
Components
Solar
4y 1m
In Queue
System Impact Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 7m
Schedule
19 months past proposed COD
Impact Study25%
Queue EntryFeb 22, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-01
Project Details
State
CA
County
Imperial
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
161 kV L line
Data Source
LBNL
No news available for this project.