BetaActiveGeothermalIIDLBNL
140 MW generation in Imperial, CA · In queue since December 2021 · Proposed COD August 2027
140 MW
Capacity
1
Components
Geothermal
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 8m
In Study38%
Queue EntryDec 30, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-01
Project Details
State
CA
County
Imperial
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
Proposed New Facility
Data Source
LBNL
No news available for this project.