175 MW hybrid in Imperial, CA · In queue since November 2021 · Proposed COD April 2024
175 MW
Capacity
1
Components
Solar
4y 4m
In Queue
System Impact Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 5m
Schedule
24 months past proposed COD
Impact Study25%
Queue EntryNov 17, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-04-01
Project Details
State
CA
County
Imperial
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
230kV KN line
Data Source
LBNL