BetaActiveSolarBatteryIIDLBNL
90 MW hybrid in Imperial, CA · In queue since November 2021 · Proposed COD October 2027
90 MW
Capacity
1
Components
Solar
4y 4m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 11m
Impact Study25%
Queue EntryNov 17, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
CA
County
Imperial
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
92kV Anza Substation
Data Source
LBNL
No news available for this project.