— Project Summary

Queue ID
IID-GI-2021-147
Capacity
75 MW
Technology
Solar+Battery
Status
active
Location
Imperial, CA
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryIIDLBNL

75 MW hybrid in Imperial, CA · In queue since November 2021 · Proposed COD April 2024

75 MW

Capacity

1

Components

Solar

4y 4m

In Queue

System Impact Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 5m

Schedule

24 months past proposed COD

Impact Study25%
Queue EntryNov 17, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-04-01

Project Details

State

CA

County

Imperial

Region

West

Developer

Utility

Imperial Irrigation District

Entity

IID

Point of Interconnection

161kV N line

Data Source

LBNL

No news available for this project.