— Project Summary

Queue ID
IID-GI-2021-144
Capacity
28 MW
Technology
Other
Status
active
Location
Imperial, CA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveOtherIIDLBNL

28 MW generation in Imperial, CA · In queue since March 2021 · Proposed COD December 2028

28 MW

Capacity

1

Components

Other

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 9m

In Study38%
Queue EntryMar 8, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

CA

County

Imperial

Region

West

Developer

Utility

Imperial Irrigation District

Entity

IID

Point of Interconnection

92kV J line

Data Source

LBNL

No news available for this project.