BetaActiveSolarBatteryIIDLBNL
30 MW hybrid in Imperial, CA · In queue since November 2020 · Proposed COD February 2026
30 MW
Capacity
1
Components
Solar
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 3m
Schedule
2 months past proposed COD
In Study38%
Queue EntryNov 16, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-01
Project Details
State
CA
County
Imperial
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
92kV R line
Data Source
LBNL
No news available for this project.