BetaActiveGeothermalIIDLBNL
140 MW generation in Imperial, CA · In queue since October 2016 · Proposed COD March 2025
140 MW
Capacity
1
Components
Geothermal
9y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
8y 5m
Schedule
13 months past proposed COD
In Study38%
Queue EntryOct 14, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-03-01
Project Details
State
CA
County
Imperial
Region
West
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Point of Interconnection
Midway Substation
Data Source
LBNL
No news available for this project.